Fonterra Boiler Auxiliary Installation
Fonterra's Heat Recovery Boiler failed which resulted in part of the plant having to shut down and PFS were brought in to urgently manufacture and install a temporary 20m stack for the relocated boilers. This was done by our site services team over a weekend. During this time some of Fonterra production at the plant was put on hold.
Te Awamutu site - installation of steam piping and header
- Fonterra's Heat Recovery Boiler failed which resulted in part of the plant having to shut down and PFS were brought in to urgently manufacture and install a temporary 20m stack for the relocated boilers.
- This was done by our site services team over a weekend. During this time some of Fonterra production at the plant was put on hold.
- PFS manufactured and installed the new header and all interconnecting pipe work to two fire tube boilers.
- Pipe work and installation was completed within two weeks to enable Fonterra to operate at full production levels.
- Due to the expertise of our site services crew the manufacture of the temporary stack was expedited and loss for Fonterra was minimised.
Location: Te Awamutu