There was a bottle neck in the process plant producing peroxide. The solution was to increase the size of the two peroxide pressure. The scope of work included:
Detailed design of the 2 peroxide pressure vessels
Procure duplex plate and domed ends and fabricate pressure vessles, prior to the shut.
Procure and pre-spool all piping and install as much as possible aheasd of the shut
Fabricate skids for pumps and specialist plant and installahead of the shut.
Fabricate all structure to fit within existing structure to support the new vessles and flooring
During the shut replace old vesselswith new.
Install new heat exchangers
Connect all pipe work
In the oxidiser tower install new trays nozzels and supports.
New manways to the tower.Customer: Evonik Peroxide Limited
Location: Morrinsville
Industry: Oil & Gas