PFS Manufactured and installed a super heater and screen tubes for the No.2 Recovery Boiler upgrade.
The project included:
- Procure boiler tubes from offshore.
- Bend tubes to different radii to suit return tubes.
- Shop manufacture the new heater banks.
- NDT and hydro test superheater tube banks.
- Crane superheater bank from the truck.
- Lower through the roof of the recovery boiler.
- Weld bank into headers.
- Bring the recovery boiler back into operation after the hydro test.