Projects | Civil Engineering Rotokauri Hub Pedestrian Bridge

Bridge over rail lines with access ramps and stairs down to platforms. Walk through lattice truss structure with SHS members and aluminium panel balustrades.

Key Features:

  • Main truss span. 
  • An Access ramp and stairs from 'The Base' to the main bridge span.
  • Walk through lattice framed truss from bridge to platforms, with precast stairs inside (two off).
  • Lift shafts with glazing and decorative panels (three off).
  • Large SHS struts and braces welded into lattice trusses to form a walk-through bridge. 
  • Aluminum panels, with laser cut design, between braces to form balustrades.

Challenges:

  • Architectural design and structural design were both 2D. Complexities of detailed coordination could only be achieved with the PFS 3D Model. PFS built the bridge to this 3D model and the new NZS5131 code.
  • Detailed design using solid works 3D model to coordinate all truces with platforms and foundations. 
  • The complex process of attaching aluminium panels to a carbon subframe faced challenges due to the dissimilar materials and thousands of fixings. PFS addressed this by redesigning the subframe, using aluminium square sections (SHS) with panels riveted directly to them. An artistic design was cut into all panels to ensure that once fitted between SHS braces it read as a single design over the length of the bridge.
  • The original design had a bolt in the top lattice truss so precast deck panels could be lifted on-site from above. This added complexity to fabrication transport and erection. PFS solved this by providing a fully welded structure and permanent deck formwork so the panels could be cast in situ.
  • Large crane lifts over rail lines during a block of line. 
  • Tight programme set around new train connection from Auckland to Hamilton. 

Andritz Oy | Pulp Mill Services

"PFS have recently undertaken the fabrication and installation of a Recovery Boiler air system upgrade at Carter Holt Harvey's Kinleith Pulp and Paper Mill in New Zealand for Andritz Oy of Finland. This work included the installation of new boiler waterwall panels, ducting and piping.

There were nine new waterwall panels installed, each consisting of six tubes 63.5 mm 00, and so in total there were 108 site welds required. Recovery boiler tube welds are 100% radio graphed and inspected to a very exacting specification. PFS achieved the unusually high standard of zero failures, which is a result they can be proud of. This is equal to world best practice. PFS manufactured and installed the ductwork including the three sets of aerofoil flow meters. This was a challenging job with tight tolerances and was well done.

We found PFS reliable, well organised, honest and easy to do business with. Their safety systems were very good. They achieved the critical time schedule required and with consistently good quality. We would be pleased to work with PFS again."

Timo La berg, Project manager

RX Plastics Ltd, Hamilton

"I like to take this opportunity to say well done to all your engineering staff that has worked on any of the rotational moulding tooling that we have sent in for modifications or repairs, the general consensus from staff members here is that they are very impressed with the finish and workmen ship that has been done. I have found the finish to be of a high standard that is comparable to an expert mould making company and we will continue to send tooling in to be repaired / modified knowing it will be good hands.

Also I would like to say well done to all the on-site service staff that have worked on tooling at our factory; this has also been complete in a very tidy manner and to a high standard. I have always found them very professional to work with."

Jamie Robertson, Maintenance Manager

CHH

"109 welds completed 100% pass rate - outstanding!

Congratulations to the PFS team for achieving their goal of 100% butt weld pass rate. This was a tough goal given our high acceptance standards and was not achieved by accident - but was a result of good planning, training, weld preparation and a team of skilled welders."

Warren Blakemore

Manager | Canpac | Fonterra

"A short email to say thanks to you and the team for the support and repair work on the incinerator last week, line has been started and heat applied. I really appreciated the professionalism of your team and their attitude to safety and engineering, please pass on my thanks"

Paul Hogben, Maintenance Services

Canpac

"I would like to write to you both to thank you for the prompt response and good capable work that was carried out at Fonterra - Canpac by your tradesmen in the repair of our Oven Incinerator. We were particularly impressed by the quiet and efficient manner that the tradesmen just got down to work and the professional manner in which the work site was organised. It was quite clear that ‘safety’ was paramount and that the men were well equipped with the resources to isolate the work space from the adjacent Production environment."

Paul Clark, Project Engineer

Responsive
Lead-time

Responsive
Lead-time

Skilled
People

Skilled
People

Integrated Design
Capability

Integrated Design
Capability

Scale &
Capacity

Scale & Capacity

New Zealand
Owned And Operated

New Zealand
Owned And Operated

Quality
Assured

Quality
Assured

Make an Enquiry Start a conversation with our team.