Maintenance | Pulp & Paper OJI Fibre Evaporators

During the September shut in 2016, we were engaged by OJI Fibre Solutions to complete the 4th effect shell and 1B lamella replacement. We had a strict deadline of 11 days to complete the work.

Key Features: 

  • The shut period began positively.
  • By the second day, the old fourth effect shell was successfully removed.
  • A 400-ton mobile crane with a stiffening rig was used for the lift.
  • The purpose was to facilitate the removal of the 60-ton vessel and lamella.

 

 

Challenges: 

  • The project was delivered late on 10th day - ahead of the original schedule.
  • The client and PFS were both pleased with the outcome on the shut and would like to thank the team that worked tirelessly to make it happen.
  • Extra steel around the support structure made it more difficult to remove the lamellas from both vessels.
  • The team worked tirelessly, day and night, despite facing: Rain, Hail, and Sunshine (sometimes all within the same          hour!)

Andritz Oy | Pulp Mill Services

"PFS have recently undertaken the fabrication and installation of a Recovery Boiler air system upgrade at Carter Holt Harvey's Kinleith Pulp and Paper Mill in New Zealand for Andritz Oy of Finland. This work included the installation of new boiler waterwall panels, ducting and piping.

There were nine new waterwall panels installed, each consisting of six tubes 63.5 mm 00, and so in total there were 108 site welds required. Recovery boiler tube welds are 100% radio graphed and inspected to a very exacting specification. PFS achieved the unusually high standard of zero failures, which is a result they can be proud of. This is equal to world best practice. PFS manufactured and installed the ductwork including the three sets of aerofoil flow meters. This was a challenging job with tight tolerances and was well done.

We found PFS reliable, well organised, honest and easy to do business with. Their safety systems were very good. They achieved the critical time schedule required and with consistently good quality. We would be pleased to work with PFS again."

Timo La berg, Project manager

RX Plastics Ltd, Hamilton

"I like to take this opportunity to say well done to all your engineering staff that has worked on any of the rotational moulding tooling that we have sent in for modifications or repairs, the general consensus from staff members here is that they are very impressed with the finish and workmen ship that has been done. I have found the finish to be of a high standard that is comparable to an expert mould making company and we will continue to send tooling in to be repaired / modified knowing it will be good hands.

Also I would like to say well done to all the on-site service staff that have worked on tooling at our factory; this has also been complete in a very tidy manner and to a high standard. I have always found them very professional to work with."

Jamie Robertson, Maintenance Manager

CHH

"109 welds completed 100% pass rate - outstanding!

Congratulations to the PFS team for achieving their goal of 100% butt weld pass rate. This was a tough goal given our high acceptance standards and was not achieved by accident - but was a result of good planning, training, weld preparation and a team of skilled welders."

Warren Blakemore

Manager | Canpac | Fonterra

"A short email to say thanks to you and the team for the support and repair work on the incinerator last week, line has been started and heat applied. I really appreciated the professionalism of your team and their attitude to safety and engineering, please pass on my thanks"

Paul Hogben, Maintenance Services

Canpac

"I would like to write to you both to thank you for the prompt response and good capable work that was carried out at Fonterra - Canpac by your tradesmen in the repair of our Oven Incinerator. We were particularly impressed by the quiet and efficient manner that the tradesmen just got down to work and the professional manner in which the work site was organised. It was quite clear that ‘safety’ was paramount and that the men were well equipped with the resources to isolate the work space from the adjacent Production environment."

Paul Clark, Project Engineer

Responsive
Lead-time

Responsive
Lead-time

Skilled
People

Skilled
People

Integrated Design
Capability

Integrated Design
Capability

Scale &
Capacity

Scale & Capacity

New Zealand
Owned And Operated

New Zealand
Owned And Operated

Quality
Assured

Quality
Assured

Make an Enquiry Start a conversation with our team.