As a contractor to Veolia Water Solutions, PFS Engineering was responsible for the installation of a demineralisation and potable water treatment plant for the Todd Energy McKee Peaker plant.
Project included:
- Installation of 2x Reverse Osmosis Skids
- Installation of 2x continuous de-ionisation skids
- Installation of filter banks, UV treatment and chemical dosing equipment
- Associated piping in schedule 80 PVC
- Double-skinned transfer lines for chemical transfer from bunded area to RO skids
- Management of electrical works, subcontracted to Wells I&E Ltd