During the September shut in 2016 we were engaged by OJI to complete the 4th effect shell and 1B lamella replacement. We had a strict deadline of 11 days to complete the work.
Key Features:
- 15 men 24 hours a day.
- 400T mobile crane lifting 60T at 20m.
- Strict health and safety requirements working amongst a turpentine plant.
- Two Evaporator effects were worked on simultaneously.
- Limited workspace.
- 100% NDT on all sealing welds.
- All weather site.