PFS Engineering was engaged by Siemens Energy Pty to design, develop, and implement a full skidding arrangement to remove and replace two 60t condenser modules for three of the Huntly power station generation units.
This included full bracing of the ground floor to the basement level to handle the increased load. PFS Engineering completed the following scope of work:
- The removal of inlet and outlet water boxes. PFS then transported the oversized units to their respective painting facility to be blasted, hydrogen peroxide treated, and re-coated with 100% solid coating.
- Full re-tube of main boiler feed pump condenser and re-coating of respective water boxes and covers.
- Installation of complete Taprogge ball cleaning system, including deflection plates and ball collector, into water boxes.
- Installation of sacrificial anodes into water boxes.